Hanjin Shipping receivership: supply lessons for buyers of packaging consumables

What the Hanjin Shipping receivership of August 2016 meant for buyers of strap and closures: cargo visibility, trade terms, buffer stock and robust packing.

Timeline · September 2016

Part of the YAKU industry timeline 2016–2026. Written as of September 2016; regulations, prices and technology may have changed since.

At a glance

  • When Hanjin sought receivership on 31 August 2016, many of its ships were refused port access with cargo aboard.
  • Packaging consumables are low in value but can stop a packing line if they are stuck at sea.
  • Knowing the carrier, the trade term and who contracted the freight decides who can act.
  • Buffer stock, split shipments and packing that tolerates delay reduce exposure.

On 31 August 2016, Hanjin Shipping said it would seek court receivership after its banks, led by the state-run Korea Development Bank, withdrew support. As Reuters reported that day, Hanjin was the world’s seventh-largest container carrier, its debt stood at 5.6 trillion won (about USD 5 billion) at the end of 2015, and ports including Shanghai and Xiamen in China, Valencia in Spain and Savannah in the United States had blocked access to its vessels amid concerns over whether port fees would be paid. The consultancy Alphaliner said a bankruptcy would be the largest ever for a container line by capacity.

Within a week, the scale was clearer. According to a Reuters report of 7 September 2016, 70 Hanjin ships had been denied access to ports and three had been seized by creditors in Singapore and China. A US bankruptcy judge granted temporary protection so that vessels could dock in US ports, and the company’s parent said it would raise USD 100 million to meet cargo commitments. One shipper, HP, told the court it had products in more than 500 Hanjin containers.

At the time of writing, in September 2016, the court process in Seoul and the recovery of cargo were still under way. The neutral lessons for buyers do not depend on how it ends.

Why packaging consumables are exposed

Strap, buckles, seals and clips are rarely the most valuable items in a supply chain. They are, however, consumed every shift. A packing line that runs out of the specified buckle or strap either stops or improvises, and improvisation with an unapproved closure is a quality risk of its own.

When a container of consumables is held offshore or at a terminal that will not release it, the buyer’s problem is not the value of the goods. It is the time until replacement stock can arrive, and the cost and paperwork of getting the original cargo released.

Who can act depends on the contract

The first questions in a carrier failure are simple, and a buyer needs to be able to answer them within hours rather than days:

Question Why it matters Where the answer is
Which carrier and vessel hold the goods? Determines whether the shipment is affected at all Booking confirmation and bill of lading
Who contracted the carrier? That party deals with the carrier, forwarders and terminals The agreed trade term and freight booking
Who holds the original bill of lading? Needed to claim the cargo when it is released Document trail from supplier, bank or forwarder
Where is risk transferred? Decides who bears loss or extra cost in transit The trade term and named place in the sales contract
What does insurance cover? Extra handling, storage and on-carriage may be costly The cargo insurance policy; ask the broker

The HP filing showed one consequence. To get its goods moving, HP proposed putting up funds to pay for delivering its cargo, with ports and stevedores able to claim their fees and costs from that money. A cargo owner may end up paying extra simply to recover its own goods, and whether the buyer or the supplier carries that cost depends on the terms they agreed before shipment.

Practical steps for consumable supply

Keep a shipment register. For each open order, record the carrier, vessel, container number and bill of lading. It takes minutes per shipment and saves days when something goes wrong.

Hold a defined buffer. Decide how many weeks of strap and closures the line needs to bridge a missed shipment, and keep that quantity as a managed reserve rather than an accident of ordering.

Split critical orders. Where volumes allow, spread consumables across sailings or carriers so one failure does not take out a whole quarter’s supply.

Approve an alternative. If a second buckle size, strap grade or supplier has already been tested and approved, an emergency order is a purchasing task rather than an engineering one.

Agree communication. Ask suppliers to confirm shipment details at dispatch and to tell you promptly if a booking changes.

Pack for delay as well as distance

A container held at anchor or discharged at an unplanned port may sit for weeks longer than expected and be handled more often. That has consequences for the goods inside:

  • Moisture. Long dwell times increase the chance of condensation. Cartons of metal components benefit from dry packing and should be checked on arrival.
  • Tension retention. Loads that settle during long storage can lose strap tension. A system that tolerates some load movement is worth considering for long or uncertain routes.
  • Extra handling. Units that may be restowed or transhipped need securing that copes with more lifts and moves than the original plan.

None of this prevents a carrier failure. It limits how much damage a delay does to the cargo.

Planning your next order

If the events of September 2016 prompted a review of consumable stock, specify the quantities, sailing preferences and packing requirements in your next enquiry. Compare woven strap, PET strap and galvanized wire buckles for your route, and send the request through the enquiry page so delivery terms are agreed alongside the product.

Sources and further reading

External references provide context. They do not certify a YAKU product or validate a particular strapping system.

Technical articles are general guidance. Joint performance, suitability and load capacity need to be verified for the actual strap, component, tool and application.

YAKU Editorial

Perspectives from YAKU on metal packaging components, product specification and the practical questions behind a purchase.

Editorial standards
More from 2016Back to the journal

Explore the components

Bring us the details.

Share your strap, component size and application. We will use them to clarify the next step in your enquiry.

Discuss your requirement
WhatsAppGet a quote

Quote list

Your quote list is empty.

Add sizes from any product page. We review pricing, availability and lead time for your enquiry.

Review and send